Job Highlight: West Los Angeles VA Medical Center
April 3, 2026

Job Highlight: West Los Angeles VA Medical Center

Advancing Infrastructure at the West Los Angeles Veterans Affairs Medical Center.

Supporting a Growing Healthcare Campus

Progress is underway on the new boiler plant at the West Los Angeles VA Medical Center, a critical addition designed to support the campus's continued growth. This new facility will play a key role in powering the upcoming patient tower and enhancing overall campus operations.

Concrete foundation and rebar for the new VA Medical Center building, with the existing hospital campus behind

A Facility Built for Performance

The 11,957-square-foot boiler plant will house boilers, essential mechanical systems, a dedicated plant operations room, storage areas, and administrative offices, creating a centralized hub for efficient and reliable system performance.

PPM field team reviewing utility trenching work at the VA Medical Center Long Beach campus

Upgrading Critical Infrastructure

In addition to the new facility, the project includes major underground utility upgrades and infrastructure improvements. These enhancements will strengthen steam and condensate systems, supporting both new construction and existing buildings across the campus.

Underground utility piping being installed in an open trench at the VA Medical Center site

Recent Milestones and Progress

The team has recently completed key excavation and concrete work for the manholes, marking an important milestone in the project's progress. With strong momentum on site, the project continues to move forward toward its next phase.

Three PPM crew members on the VA Medical Center Long Beach jobsite